French power company EDF said the new nuclear plant it is building at Hinkley Point C will cost up to £ 2.9bn more than thought.
It raised its estimate for the project, in Somerset, to between £ 21 .5bn and £ 22 5bn, blaming “challenging ground conditions”.
It also said the risk of the project being 15 months late had risen.
In common with other major UK building projects, such as Crossrail and HS2, the power plant is over budget.
EDF last raised its estimate for the project in 2017, by £ 1.5bn.
Cheap wind
Because of the way that the project is being funded, taxpayers and customers will not foot the bill for the increase in costs – EDF and CGN will pay. But part of their risk is covered by a comparatively high unit cost for customers.
“This is clearly bad news for nuclear new build prospects in the UK, particularly in light of recent record low offshore wind prices, “said Investec analyst Martin Young.
Last week, prices for new wind power delivered by 2025 were set at prices as low as £ 40 per megawatt hour. By comparison, power from Hinkley Point C is expected to cost £ 92. 50 per megawatt hour.
While EDF and China General Nuclear Power Corp (CGN), which is partnering the French firm on the work, are still aiming to finish in 2025, the chance of that being 2026 has risen.
“We’ve given the best view we can, given what we know,” Paul Spence, EDF’s director of corporate and regulatory affairs, told the Today program. “I can’t say today what will happen over the course of the construction.”
The project is not alone in being complex, late and
The first phase of the HS2 high-speed railway between London and Birmingham will be delayed by up to five years, Transport
Its cost has also risen from £ 62 bn to between £ 81 bn and £ 88 BN.
Crossrail, the new railway line bisecting London from Reading to Shenfield, was due to be operating by December. The project was allocated £ 14 .8bn in 2010, but this has since swollen to £ 17. 6bn, and is likely to rise further, according to a report by MPs.
“Cost increases reflect challenging ground conditions which made earthworks more expensive than anticipated, revised action plan targets and extra costs needed to implement the completed functional design, which has been adapted for a first-of-a-kind application in the UK context, “EDFsaid in a statement.